Read the guideThe short answer: production rarely causes late launches — calendars slip in feedback delays, fabric lead times and approvals that nobody scheduled. This guide builds a realistic calendar from proto to delivery and gives MOQ a decision framework instead of a sticker price.
Sampling is not a delay before production — it is where bulk risk is bought down. Each round has a different job.
| Round | Purpose | Typical demo timing demo |
|---|---|---|
| Proto | Prove the pattern, fabric direction and construction route on your actual style | 7–10 days after complete inputs |
| Fit sample | Grade across the size run; solve roll-down, band tension, edge comfort | 5–7 days after proto comments |
| PP (pre-production) | Lock bulk fabric, trims, labels and finishing — the reference bulk is judged against | 5–7 days after fit approval |
| Shipped / TOP | Verification only — a production-line piece pulled and checked against PP | Within the first production days |
Timings are demo figures for planning, not commitments; each round's clock starts when complete inputs arrive — fabric refs, measurements, comments, labels. Incomplete inputs are the most common silent delay.
The question is never "what's your MOQ?" — it's "what does the MOQ buy, and what does going under it cost?"
| Driver | Why it moves MOQ | What to ask |
|---|---|---|
| Fabric minimums | Mills sell by yarn lot and dye batch; a custom color may need hundreds of kilos | Which fabric minimum drives this MOQ — and is a stock color an option? |
| Size-run coverage | A 6-size run spread over a small total means tiny per-size cuts that waste setup | Per-size minimums, not just style minimums |
| Color count | Each color re-buys fabric and changes over lines | MOQ per color vs. combined; surcharge for small color runs |
| Custom level | Full custom knit + custom trims carries higher minimums than library fabrics | What library options exist at lower quantity |
| Reorder intent | Factories price first orders on the relationship, not the single PO | Reorder terms and whether MOQ flexes on repeat orders |
Our own MOQ and sampling terms are published on the OEM services page with demo figures pending final confirmation — the framework above is how we set them, and how we suggest you read any factory's numbers.
Bulk lead time is a stack of three clocks, and the longest one wins.
Yarn procurement, knitting, dyeing and finishing — typically the longest pole for custom colors. Demo range: 2–4 weeks for stock-ish knits, longer for custom dye lots. demo
Cutting, sewing, bonding or seamless knitting, finishing and packing. Our demo production window is 7–12 days for typical orders once materials land. demo
Labels, hangtags, test reports and market paperwork. Usually short — unless discovered late, when it becomes the only clock anybody talks about.
Then add shipping, which is a mode decision: express days, air roughly a week door-to-door with clearance, sea several weeks by lane. Decide the mode when you sign the PO, because it changes how much buffer the calendar needs — and sometimes which factory can even make the date.
A first-time brand orders one bodysuit, five colors, standard size run, launch at week 16. With complete inputs on day one, the demo calendar stacks like this: RFQ and factory verification, weeks 1–2; paid proto plus comments, weeks 3–5; fit sample round, weeks 6–7; fabric booking on approval, weeks 8–11; PP sample in parallel, week 11–12; production weeks 12–14; packing and inspection week 14; sea freight to arrive week 16 — with the air option as insurance if any round slips.
Now the same order where feedback takes ten days instead of two at each round: that's roughly five extra weeks hiding in what felt like "waiting for the factory". The factory didn't slow down; the calendar was never scheduled around replies and approvals.
That is the entire argument of this guide: the calendar is a shared document. A factory that sends it unprompted — rounds, clocks, buffers and decision dates — is showing you how it thinks about your launch.
Materials can be pre-booked against a strong proto result — we do this for tight calendars — but cutting waits for PP approval. Producing bulk off an unapproved sample just moves the risk to a place where it costs ten times more to fix.
In our experience: late or incomplete buyer inputs (measurements, label files, comments), custom dye lots discovered mid-sampling, and approvals that queue behind holidays on either side. Almost none of it is sewing speed.
We work with first-order minimums and library-fabric options designed for smaller runs — the specifics are on the OEM services page. The honest framing: below a certain quantity, unit economics stop working for both sides, and a good factory tells you that plainly instead of taking the order.
Send your styles, quantity and launch date. We'll return the quotation with a sampling-and-production calendar attached — rounds, clocks, decision dates and the shipping-mode buffer, in one document.